How to Write a Rehab Scope of Work for a Florida Flip
Blog

How to Write a Rehab Scope of Work for a Florida Flip

November 26, 2026 · 8 min read · By Onias Derilus, Broker

The scope of work is the document your contractor bids on, your lender draws against and the permit office reads. Here is how to write one line by line.

A rehab scope of work is the written list of every repair a flip needs. Each line says where the work is, what gets done, how much of it, and what materials go in. It is the document your contractor bids on, your lender builds its draw schedule from, and the permit office reads. So write it before you make an offer, not after you close. This guide shows Florida investors how to build one that holds up from the first bid to the final inspection.

Key takeaways
  • Write the scope before you offer, so the price you pay reflects the real repair bill.
  • Start with the roof, structure and systems, then move to finishes.
  • Give every line a location, a quantity, a material spec and a finish standard.
  • Send the same scope to every contractor so the bids compare line for line.
  • Hard money lenders turn the scope into draws, so a vague line can hold up your money.

What a rehab scope of work does

The scope has three jobs. First, it sets the budget. You cannot price a flip until you know what you are fixing, and the scope is that list. Second, it lets you compare contractors. When three bids price the same lines, you can see who is high, who is low and who left something out. Third, it feeds the lender and the building department. A hard money lender reads it to decide how much rehab money to lend, and the permit office reads the parts that need a permit.

A loose scope fails at all three. "Redo kitchen" can mean painted cabinets or a full gut with a new layout, and two contractors will read it two ways. A tight scope removes that guesswork. It also protects you later, because a written line is what you point to when a job is half done.

Start with a full walkthrough

Walk the house with a notepad, a camera and a tape measure. If you can, bring your contractor or a home inspector. Go room by room and floor to ceiling, and photograph every problem you see. Then go outside and do the same for the roof, the yard, the driveway and the drainage.

Systems and structure first

Begin with the items that cost the most and that buyers and insurers check first. That means the roof, the electrical panel and wiring, the plumbing supply and drain lines, the air conditioning, the water heater and any sign of structural trouble. In Florida, also look for wood rot, termite damage, cracked slabs and water stains on ceilings. A sewer camera on the main drain line is worth the cost on older homes, since a broken line under a slab changes the whole budget.

Then the finishes

Once the systems are listed, move to what buyers see. That covers flooring, paint, doors, trim, kitchen cabinets and counters, bathrooms, lighting and landscaping. These lines are easier to price, and they are also where you can adjust the budget to fit the resale price.

How to write a rehab scope of work line by line

Each line should answer the same six questions. Where is the work? What is the task? How much of it is there? What material or model goes in? Who supplies the material? And what does "done" look like? Here is how that reads in practice.

  • Kitchen. Remove existing cabinets and counters. Install 22 linear feet of shaker cabinets, owner-supplied, and quartz counters, contractor-supplied. Done means installed, sealed and plumbed, with the sink and disposal working.
  • Living areas. Remove carpet from 1,100 square feet. Install luxury vinyl plank, owner-supplied, with new baseboards. Done means trimmed, caulked and painted.
  • Main bath. Demolish the tub and surround. Install a tiled walk-in shower with a new valve. Done means passed inspection, grouted and sealed.
  • Electrical. Replace the main panel with a 200-amp panel. Done means permitted, inspected and labeled.

Notice what those lines avoid. They do not say "update" or "as needed," and they do not leave the material open. Use measurements from your walkthrough, not guesses. When you are unsure of a quantity, write "contractor to verify" so the bid spells it out.

Group the lines by trade and by order

Sort the list into phases: demolition, structure and roof, rough plumbing, electrical and air conditioning, insulation and drywall, then finishes. That order matches how the work happens on site. It also matches how most lenders release rehab money, which makes the next step easier.

Florida items every rehab scope of work should address

Some lines matter more here than in other states, because insurers, codes and flood rules focus on them.

  • Roof. Florida law has a special rule for partial roof work. Under section 553.844, if a roof was built or replaced under the 2007 Florida Building Code or later, and 25 percent or more is repaired, only the repaired part must meet the current code. An older roof does not get that exception. So note the roof's age and code history in the scope.
  • Windows and doors. Exterior openings must meet wind-load rules and carry a product approval. List the brand and the approval, since the permit office will ask.
  • Flood zone work. In a FEMA flood zone, large projects can trigger the substantial improvement rule. Federal rules in 44 CFR 59.1 define it as work costing 50 percent or more of the structure's market value. Past that line, the whole house may need to meet flood rules.
  • Septic. Many older Florida homes are on septic. A repair or replacement needs its own permit, separate from the building permit, so give it its own line.

Turning the scope into bids

Send the exact same document to every contractor. Ask each one to price every line, not just to give a total. Then you can compare apples to apples, and you will spot the bid that skipped the drain line or the panel. A lump-sum bid with no detail is hard to manage later, because you cannot tell what a change should cost.

Before you hire, check the license on the state's Department of Business and Professional Regulation site. Florida law is blunt about this. Under section 489.128, a contract made by an unlicensed contractor cannot be enforced by that contractor. Our guides to finding house flip contractors and hiring a contractor in Palm Beach County cover vetting in more depth.

Attach the final scope to the signed contract. That way the scope and the contract say the same thing, and there is one list for everyone to work from.

How lenders use your rehab scope of work

A hard money lender lends mostly on the property and the plan. So the lender reads your scope next to the purchase price and the after-repair value, often called ARV. If the budget looks too thin for the work listed, the lender may lend less or ask for more cash. If it looks padded, the lender may question the deal.

Most fix-and-flip loans hold the rehab money back and pay it out in draws as work is finished. The lender's inspector checks each phase against your scope before money is released. That is why a vague line causes trouble. If the scope says "bath remodel" and the inspector sees tile but no vanity, nobody knows whether the line is done. Our guide to the hard money draw schedule shows how phases map to draws.

For the rest of the file, see hard money loan requirements in Florida and our overview of fix and flip loans. Mortgage Capital also keeps a summary of its hard money loan program.

Contingency and change orders

Every rehab finds something the walkthrough missed. So add a contingency line at the bottom of the budget, and size it to the age and condition of the house. Older homes deserve a bigger cushion. For example, assume a $60,000 budget with a 10 percent contingency. That line would be $6,000, and it covers surprises without a new loan request.

When the work changes, write it down. A change order should name the line it changes, the new price and the new finish date, and both of you should sign it. Verbal changes are how budgets drift. They are also how disputes start, since neither side can prove what was agreed.

Match the rehab scope of work to the permit

Mark every line that needs a permit, such as the roof, windows, panel, plumbing and structural changes. Then make sure the permit covers all of them. Work done outside the permit can fail inspection, stall a draw or surface later in the buyer's permit search. Our guide to remodel permits in Florida lists the common projects.

Florida also has a lien law step that ties in here. Under section 713.135, when the direct contract is over $5,000, a copy of the recorded notice of commencement must be filed with the permit office before the first inspection. If you are borrowing, talk to your lender before you record it, because the order of recording matters.

Write the scope for the buyer you will sell to

The finish level should fit the price you expect to sell for. Too little and the house sits. Too much and you spend money the buyer will not pay back. Before you pick finishes, look at recent sales of similar homes nearby. Our market reports show prices and days on market, and city pages for West Palm Beach, Port St. Lucie and Boynton Beach show what is listed and what has sold.

A listing agent who sells in that area can also tell you which upgrades buyers notice there. Ask before you order cabinets, not after.

Selling a house that needs work?

Owners can use the same idea. When an investor makes an offer on a house that needs repairs, the offer is built on the investor's own scope and budget. Knowing roughly what your repairs involve helps you judge whether the discount is fair. Start with a home value estimate for the house as it is. Then run the numbers in our home sale calculator to compare a cash sale with a listing.

Have a scope and a deal? Send us the purchase price, the scope and your ARV, and we will help you line up the financing.

Get a fix-and-flip term sheet or see what a property is worth today.

Frequently asked questions

Who writes the rehab scope of work, me or my contractor?

You should. A contractor can help you measure and add lines, but the scope is your plan. If the contractor writes it, you are comparing other bids against one contractor's view of the job.

How detailed should the scope be?

Detailed enough that two contractors would price the same work. Each line needs a location, a quantity, a material and a finish standard.

Does the lender need the rehab scope of work before closing?

Usually, yes. Most fix-and-flip lenders review the budget and scope before they set the loan amount and the draw schedule.

Can I change the scope after closing?

Yes, but put each change in writing and tell your lender. A change can shift the draw schedule, the permit and the budget.

Should the scope include permits and fees?

Yes. Add lines for permit fees, inspections, dumpster rental and cleanup. They are real costs, and they are easy to forget.

Related reading

Sources

Onias Derilus

About the author

Onias Derilus

Broker · Florida Real Estate Broker · FL License BK3276618

Reviewed and published by the Pure Equity team, led by broker Onias Derilus. We help clients buy, sell, rent, and invest across South Florida's eight counties. Meet the team.

Talk to an Expert

Our team is happy to answer any questions this article raised, or give you a personalized take on your specific situation. No pressure, no pitch.

By submitting you agree to our Privacy Policy and Terms of Use.

Areas We Cover

Show All Areas

More Florida cities

Palm Beach County ZIP codes

Communities